The 2018 Project of the Fiber Optic System for the Trogir – Čiovo Bridge

Projekt svjetlovodnog sustava Mosta 1

The bridge between Trogir and Čiovo was built for more than three years and was officially opened in July 2018. The main goal of the bridge construction is to avoid traffic congestion during the tourist season, as well as to relieve traffic from the old town of Trogir, which is under UNESCO protection.

Most Trogir – Čiovo u završnici izgradnje

The Trogir–Čiovo Bridge – Nearing Completion

Due to unforeseen problems, the completion of the works was postponed several times. The bridge automation system, responsible for light signaling and bridge lifting, failed. Our company STE d.o.o. was engaged to eliminate the problem and find a solution.

Dio sustava upravljanja i prometne signalizacije mosta

A part of the bridge management and traffic signaling system.
Ask ChatGPT

Dio sustava upravljanja i prometne signalizacije mosta i dijagnostika funkcionalnosti svjetlovodnog sustava

A part of the bridge management and traffic signaling system, including diagnostics of the fiber optic system functionality.

A part of the bridge management and traffic signaling system, including diagnostics of the fiber optic system functionality.

Implementation of single-mode and multi-mode cables

During the inspection and measurements, we detected a problem. During the installation process of the fiber optic system, a mix of multi-mode and single-mode fiber optic cables occurred, which led to the entire bridge automation system not functioning. In order to resolve this situation, we first installed the appropriate equipment to properly connect all parts of the fiber optic system.

Intervencija i otklanjanje nefunkcionalsnosti svjelovodnog sustava

Intervention and troubleshooting of fiber optic system malfunction.

Intervencija i otklanjanje nefunkcionalsnosti svjelovodnog sustava

Intervencija i otklanjanje nefunkcionalsnosti svjelovodnog sustava

Thus, the internal automation and signaling system of the bridge was solved with multi-mode, while communication to the outside towards the so-called main fiber optic system was realized with single-mode fiber optic technology.

Detalji iz nadogradnje zatečenog svjetlovodnog sustva

Details from the upgrade of the existing fiber optic system.

Detalji iz nadogradnje zatečenog svjetlovodnog sustva

Details from the upgrade of the existing fiber optic system.

We collaborated with STRABAG on this project, especially in the part of changing the existing technological solution of the bridge’s movable structure in order to ensure the correct functioning of the automation system.

Conclusion

Despite the challenges encountered, we successfully found a solution within the set deadline. The complete automation and signaling of the bridge were resolved using a combination of multi-mode and single-mode fiber optic technology.

Provjera funkcionalnosti upravljanja pokretnih dijelova mosta – podizanje kraka za propuštanje plovila

Verification of the functionality of movable bridge components – lifting of the span for vessel passage.

Through the experience of working on this project, thanks to the high professional qualifications of our team and cooperation with other personnel on the construction site, we have demonstrated the ability to solve such challenges, especially in situations that require quick and timely reactions and solutions.

Završnica projekta i momenti koji se pamte

Project completion and memorable moments.

 